Short answer: inside the Village of Greenwood Lake, a new driveway, a changed entrance onto a village road, or work within 25 feet of the road's center line needs a permit from the Village Building Inspector first. The driveway must be paved at least 25 feet from the road, and fully paved if it is steeper than a 10% grade.
1. Check which roads and offices are involved
Any new driveway inside the Village of Greenwood Lake needs a Chapter 117 permit. If your driveway meets a county road or a state highway, you may also need that agency's permit. Our driveway permits guide explains who handles which road.
2. Check whether your work needs a permit
You need a permit before you:
- install a new driveway,
- change an existing driveway entrance onto a village road, or
- do any work within 25 feet of the center line of a village road that affects the road.
3. Contact the Building Inspector
The permit comes from the Village of Greenwood Lake Building Inspector, and it must be issued before work starts.
4. Have plans ready if asked
If the Building Inspector decides plans are needed, the village asks for two copies, certified by a New York State land surveyor, architect or certified engineer.
5. Provide the contractor's insurance certificate
The Building Department needs a certificate of contractor's liability insurance naming the Village of Greenwood Lake as certificate holder. The code sets minimum coverage of $1,000,000 for bodily injury and $100,000 for property, plus evidence of workers' compensation insurance. Ask your contractor for this before you hire them; see 10 questions to ask a paving contractor.
6. Pay the fees and deposits
Before the permit is issued, the applicant pays the fees and deposits set in the Village of Greenwood Lake Fee Schedule. Ask the Building Department for the current amounts.
7. Build to the village standards
| Rule | What the code says |
|---|---|
| Paved apron | At least 25 feet paved from the edge of the village road, with no less than two inches of blacktop, asphalt, concrete or pavers. |
| Steep grades | Driveways over a 10% grade must be paved for their entire length. |
| Maximum steepness | No driveway grade may exceed 15%. |
| Drainage pipe | Where a pipe is required, it must be at least what the Building Inspector requires after consulting Public Works, with at least four inches of cover over the pipe. |
| Very long lanes | Driveways over 1,000 feet long from a state, county or municipal road need markings approved by the Building Department, to help fire and emergency services. |
| Build as approved | The driveway must be built according to the plans and specifications submitted. |
A 10% grade means the driveway rises 1 foot for every 10 feet of length. On a hillside lot, check the grade before planning a stone driveway.
8. Know the penalties and how to appeal
Breaking the chapter is a violation punishable by a fine of up to $250, up to 15 days in jail, or both, and each day it continues counts as a separate offense. Appeals and requests for variances go to the village Zoning Board of Appeals.
This guide summarizes the village code for general information. It is not legal advice. Confirm current requirements and fees with the Village of Greenwood Lake Building Department before work starts.
Questions people ask
Do I need a permit to repave my driveway in the Village of Greenwood Lake?
If you are installing a new driveway, changing the entrance onto a village road, or working within 25 feet of the road's center line, yes. For other resurfacing, ask the Building Department before work starts.
Can my driveway be steeper than 15%?
Not under the village code, which sets 15% as the maximum grade. The Zoning Board of Appeals hears requests for variances.
Last checked November 12, 2026.